AdvancedSectionCompositeTransformed section

Composite bridge deck — a concrete slab on a steel plate girder

The same steel girder, connected to a slab that was going to be cast anyway, is three times stiffer. That factor is the entire commercial argument for composite construction — and it rests on one dimensionless number and a row of shear studs.

Figure 1.A concrete slab on a steel plate girder, with each material’s own centroid and the transformed centroid between them.
Given
Girder
300×20 flangesweb 12 × 600
Slab
2 000 × 200EFFECTIVE width
200 GPa
≈ 28.6 GPa
1/7
1

Part 1 — A girder, a slab, and one number that joins them

Two materials, drawn edge to edge.

A welded plate girder, drawn as three rectangles about the centerline:

REC -150,0 150,20 bottom flange 300 × 20 · REC -6,20 6,620 web 12 × 600 · REC -150,620 150,640 top flange 300 × 20

Then the slab, sitting on the top flange: REC -1000,640 1000,840 — 2 000 wide, 200 thick.

Now the part that makes it composite. In the Material group, add a second material, set its modular ratio to n = 0.1429 (that is 1/7, taking GPa and GPa), select the slab, and press Assign. Give it a grey fill so the drawing reads like a section through a deck.

The properties panel immediately changes its heading to Transformed section, which is the tool telling you that every number below it is now an equivalent-steel number.

Figure 2.The section: a welded plate girder with a 2 000 × 200 concrete slab on top.
2

Part 2, step 1 — One ratio turns two materials into one section

And the arithmetic is short enough to check.

Concrete is roughly a seventh as stiff as steel, so a square millimetre of it carries a seventh of the force at the same strain. The transformed section trades area for that:

Steel 19200 mm², concrete 400000 mm²:

Then the centroid is the area-weighted average, exactly as always:

The steel’s own centroid is at 320 mm and the slab’s at 740 mm. The transformed centroid lands at 634.4 mm — pulled up out of the steel and into the top flange region, which is the whole reason the girder gets stiffer.

Figure 3.Three centroids: the steel’s own (hollow), the slab’s own (hollow), and the transformed centroid between them (solid).
3

Part 2, step 2 — Three times the stiffness, for concrete you already had

This is why shear studs exist.

The bare steel girder has = 1.370 × 10⁹ mm⁴. Acting compositely with the slab, the same steel gives 4.095 × 10⁹ mm⁴ — a factor of 2.99.

Nothing was added to the steel. The slab was going to be cast regardless; all that changed is that it is now connected to the girder well enough to act with it. That connection is a row of welded shear studs, and its entire job is to carry the horizontal shear at the interface so the two do not slide past one another.

Without studs the two bend independently, and you are back to 1.370 × 10⁹ plus a slab spanning transversely. With them, you get the number above.

4

Part 2, step 3 — Getting real stresses back out

The transform is a device; the materials are real.

The transformed section gives stresses in the reference material — steel here — directly from the familiar formula:

For the concrete you have to undo the transform. The trick works because strain is continuous across the interface while stress is not:

With , concrete at the same height carries a seventh of the steel stress — which is the point of putting it in compression at the top, where concrete is good, and leaving the tension to the steel at the bottom, where it is not.

The section moduli tell the same story: 6455472 mm³ to the steel soffit against 19915338 mm³ to the top of the slab, because the centroid has moved so far up that the bottom fibre is now much further away than the top.

Hand calculation vs the tool

Verified — hand calculation vs the solver, to round-off
QuantityBy handStructureCalcs
Steel area300×20 + 12×600 + 300×20 = 19 200 mm²19200 mm²
Concrete area2 000 × 200 = 400 000 mm²400000 mm²
Transformed area19 200 + 400 000/7 = 76 342.9 mm²76343 mm²
Transformed centroidarea-weighted, between 320 and 740634.4 mm
Bare steel Ixthe control1.370 × 10⁹ mm⁴
Composite Ixmust be several times the bare value4.095 × 10⁹ mm⁴ · ×2.99
Plastic modulus Sxneeds f_y per material — NOT nnot reported (see below)

Every value was worked by hand with the classical method, then checked against this site’s solver — the same engine the Try it button opens. This agreement is re-run automatically on every build.

Now make it yours

Open this exact model in the calculator — then change a load, drag a support, and watch every diagram update in real time. The best way to build intuition is to break it and see what happens.

Take it with you

Export this worked example as a PDF, or download it as a .screport and open it in the Report Builder — the model travels inside the file, so you can reconstruct it, re-solve, and build your own report from it.

Verifying your link…